Through the bridge we will have a shortened distance 72 times, it will have a length of 310 meters with three arches of option C1, and it will be able to be used by cars, buses, trucks, bicycles. There is a height that allows passage under it, in case the Buna River will be open for boats. We are in the phase of preparing the detailed project that will be ready within two months. The budgeting and procurement process will take six months until June 2023, the estimated cost is around nine million euros and can be ready in 18 months.