[ad_1]
From yesterday morning, the work for the repair of the breakdown in the 35Kv line Korça-Bilisht continues, which supplies energy to the city of Bilisht and the villages around it.
The cause of the breakdown was the damage of 13 pillars where 6 of them were completely broken while 7 others partially.
The DSO has engaged 57 of its employees in the field, in a swampy terrain with a snow thickness of 30 cm, they are continuing the work for the placement of all pillars.
Currently, 4 of the broken pillars have been placed while the work continues and for the erection of 4 more, where two of them are intermediate pillars. While 3 pillars that were partially damaged have been repaired and work continues for 4 more.
In support of the brigade of TL South East is a working group of OST who are working intensively to restore energy as soon as possible to all subscribers.